Tag Archives: Federal Energy Regulatory Commission

DOE Plans Process for Designating National Interest Electric Transmission Corridors

On May 9, 2023, the U.S. Department of Energy (DOE) issued a notice of intent to establish a process for designating “route-specific” National Interest Electric Transmission Corridors (commonly referred to as “NIETCs,” pronounced \NIT-sees\)—setting in motion an anticipated shift in the balance of transmission permitting authority between the federal and state governments.

As we’ve previously noted, DOE has statutory authority to designate transmission-constrained or congested geographic areas,… More

FERC Proposes to Implement Expanded Transmission Siting Authority

On December 15, 2022, the Federal Energy Regulatory Commission (“FERC”) issued a notice of proposed rulemaking in which the Commission proposes to implement its newly clarified authority under the 2021 Infrastructure Investment and Jobs Act (“IIJA”) to issue permits if a state denies an applicant’s request to site transmission facilities in a designated National Interest Electric Transmission Corridor (“National Corridor”).

Such change has potential—in certain cases—to tilt the balance of transmission permitting authority toward FERC and away from the states (where such authority traditionally has been held),… More

D.C. Circuit Decision Upholds Access to Wholesale Markets for Energy Storage Resources, but Will More Litigation Follow?

On July 10, 2020, the D.C. Circuit upheld FERC Order 841, the landmark order requiring wholesale markets to allow participation by energy storage resources.  Challengers had contended that by prohibiting states from barring energy storage resources on the distribution system from participating in wholesale markets, FERC had exceeded its jurisdiction and infringed on state authority.

The D.C. Circuit rejected those claims. … More

FERC Authorizes Deferred Implementation of Seven NERC Reliability Standards

The Federal Energy Regulatory Commission (“FERC” or “Commission”) recently issued an Order approving a request by the North American Electric Reliability Corporation (“NERC”) to defer the implementation of several Reliability Standards scheduled to take effect later this year. This action, along with others discussed in an earlier post here, are the latest measures approved by FERC that demonstrate the Commission’s intent to exercise discretion in easing reliability compliance burdens in light of the national emergency related to the coronavirus pandemic.… More

District of Massachusetts Reaffirms Broad Defense of Filed Rate Doctrine

An important legal doctrine for companies that buy and sell in regulated markets is the “filed rate” doctrine, which limits legal challenges to rates determined by regulators such as the Federal Energy Regulatory Commission or the Federal Communications Commission. A recent decision by the District of Massachusetts illustrates the potential breadth of the doctrine.

By way of background, two class action lawsuits filed in the District of Massachusetts alleged that Eversource and Avangrid systematically abused their influence in the natural gas transmission market in violation of federal and state antitrust laws.… More

Seventh Circuit Upholds Illinois ZEC Program for Struggling Nuclear Units

On September 13, 2018, the Court of Appeals for the Seventh Circuit affirmed the trial court’s dismissal of claims that the zero-emission credit (ZEC) program enacted by the Illinois legislature in 2016 violated the U.S. Constitution’s dormant Commerce Clause and was preempted by the Federal Power Act. The Court took the unusual step of requesting an amicus brief from the Federal Energy Regulatory Commission (FERC). … More

Escalation of Cybersecurity Threats to National Power System Prompts FERC to Call for Stricter Reporting Standards

On July 19, the Federal Energy Regulatory Commission (“FERC” or “Commission”), pursuant to its authority under section 215 of the Federal Power Act, issued a final rule directing the North American Electric Reliability Corporation (“NERC”) to develop modifications to NERC’s Reliability Standards as they relate to cyber security incidents. Issuance of the final rule is timely. A recent news article described hackers’ successful infiltration of the control rooms of multiple electric utilities.… More